- Phases 1 & 2 - 48 slips 35 to 80 feet
- Total slips – 106 all phases
- Project competed within City's budget and on schedule in time for Summer Festival event
- Bulkhead rehab and waterfront promenade
- Inspected original bulkhead structure
- Fixed heavy timber dock construction
- Completed boating traffic study as part of permitting phase
- Coordinated for relocation of navigation channel
- Wastewater disposal pumpout tied to city sewer system
- Realigned Stewart Parkway
- Provided event power along Stewart Parkway
- Constructed in flood hazard area
- Relocation of federal channel required for Phase 1 and Phase 3 projects
- Environmental Assessments for initial 48 slips and Phase 3 expansion
- Marine power systems
- Designed timber walkway and railings for N. C. Estuarium waterfront
- Ferry landing dock, mooring dolphins & power
- Included low freeboard small craft floating access dock
- Phase I funded by CAMA grant
- Phase 2 funding facilitated by Clean Water Trust Fund funding for downtown storm water treatment system