Front Street Village

The Boathouse at Front Street Village

Beaufort, North Carolina

Front Street Village, LLC

Bucky & Wendy Oliver, Beaufort, NC

Project Engineer: J.W. (Bill) Forman, Jr., P.E.

Project Highlights

  • Re-development of former menhaden fish products factory
  • Dry storage marina, 2 buildings with over 400 dry slips
  • Concrete boat launching platform, integrated with bulkhead
  • Bulkhead and boat launching platform in Phase 1
  • 785 L.F. of steel sheet pile bulkhead with concrete cap
  • Floating docks with concrete guide piles
  • Site work for multi-use hotel and waterfront restaurant
  • Use of pervious pavers as a stormwater BMP
  • Site planning by Sears Design Group
  • Dredging and upland disposal
  • Required CAMA Major permitting and modifications
  • Storm water management with stormwater reuse
  • Realignment and widening location of Lennoxville Road
  • Relocation of Front Street intersection
  • Use of underground sand filters as stormwater BMP
  • Erosion control design and permitting
  • Extension of Town of Beaufort water distribution and sewer collection systems
  • Design of three lift stations and force main to Town of Beaufort wastewater treatment plant