252.622.4338
Moss Landing Condominiums

Washington Waterfront & Marina

Washington, North Carolina

The Client

City of Washington
Bobby Roberson, Teresa Hamilton & Phillip Mobley

Project Status

  • Phase 1 Completed, 2006 100%
  • Phase 2 Completed, 2006 100%

Project Engineer: J.W. (Bill) Forman, Jr., P.E.

Bulkhead rehab and waterfront promenade; Total 106 slips - 35 to 80 feet;

Project completed within City's budget and on schedule in time for Summer Festival event!

Designed timber walkway and railings for N. C. Estuarium waterfront.

Project Highlights

N

Phases 1 & 2 - 48 slips 35 to 80 feet

N

Total slips – 106 all phases

N

Project competed within City's budget and on schedule in time for Summer Festival event

N

Bulkhead rehab and waterfront promenade

N

Inspected original bulkhead structure

N

Fixed heavy timber dock construction

N

Completed boating traffic study as part of permitting phase

N

Coordinated for relocation of navigation channel

N

Wastewater disposal pumpout tied to city sewer system

N

Realigned Stewart Parkway

N

Provided event power along Stewart Parkway

N

Constructed in flood hazard area

N

Relocation of federal channel required for Phase 1 and Phase 3 projects

N

Environmental Assessments for initial 48 slips and Phase 3 expansion

N

Marine power systems

N

Designed timber walkway and railings for N. C. Estuarium waterfront

N

Ferry landing dock, mooring dolphins & power

N

Included low freeboard small craft floating access dock

N

Phase I funded by CAMA grant

N

Phase 2 funding facilitated by Clean Water Trust Fund funding for downtown storm water treatment system

Urban design by Allison Platt & Associates